Buy S11 Oil-Immersed Transformer Suppliers – 110kV level three-phase on-load tap-changing power transformer – JSM TRANSFORMER

Buy S11 Oil-Immersed Transformer Suppliers – 110kV level three-phase on-load tap-changing power transformer – JSM TRANSFORMER

  • product details
  • FAQ
  • Download
  • Related Video
  • Feedback (2)
All we do is usually affiliated with our tenet " Buyer to start with, Belief to start with, devoting about the food packaging and environmental defense for 66kv Substation, 33kv Switchgear, Single Transformer, The continual availability of high grade products in combination with our excellent pre- and after-sales service ensures strong competitiveness in an increasingly globalized market.
Buy S11 Oil-Immersed Transformer Suppliers – 110kV level three-phase on-load tap-changing power transformer – JSM TRANSFORMER Detail:

110kV LEVEL THREE-PHASE ON-LOAD TAP-CHANGING

ELECTRIC POWER TRANSFORMER

Summary

We have adopted series of important reforms on the 110kV level three-phase oil-immersed on-load tap-changing transformer referring material,
process and structure. The transformer has the features of small size, light weight, high efficiency, low loss, low noise, reliable operation etc,
which can reduce a large amount of power network loss and operation expenses with significant economic beneffts. It is suitable for power plant substation,
heavy section plant ore enterprises etc.

图片1

Main 110kV level three-phase on-load tap-changing power transformer technical parameters
Rated
Capacity
(kVA)
Voltage Combination Vector Gourp No-load Loss Load Loss No Load
Current
Short Circuit
Impedance
%
HV
(kV)
LV
k(V)
kW kW %
6300 6.3
6.6
10.5
11
YNd11 7.40 35.0 0.62 10.5
8000 8.90 42.0 0.62
10000 10.50 50.0 0.58
12500 12.40 59.0 0.58
16000 15.00 73.0 0.54
20000 17.60 88.0 0.54
25000 110±2*2.5% 20.80 104 0.50
31500 115±2*2.5% 24.60 123 0.48
40000 121±2*2.5% 29.40 148 0.45
50000 35.20 175 0.42
63000 41.60 208 0.38
75000 13.8
15.75
18
21
47.20 236 0.33 12-14
90000 54.40 272 0.30
120000 67.80 337 0.27
150000 80.10 399 0.24
180000 90.00 457 0.20

Note 1:-5% tapping position is maximum current tapping.
Note 2: For boost transformer, it is advisable to adopt non-tapping structure. If there is any requirement for operation, sub-connectors can be set up.
Note 3: When the average annual load rate of transformer is between 42% and 46%, the maximum operating efficiency can be obtained by using the loss value in the table.

6300kVA-63000kVA three-phase three -winding NLTC power transformer
Rated
Capacity
(kVA)
Voltage Combination Vector Group No-load loss
kW
Load loss
kW
No load current
%
High Voltage
kV
Med-ium Voltage
(kV)
Low Voltage
(kV)
Step down
6300 8.9 44.00 0.66
8000 10.6 53.00 0.62
10000 12.6 62.00 0.59
12500 33 6.3 14.7 74.00 0.56 H-M
16000 110±2*2.5% 35 6.6 YNyn0d11 17.9 90.00 0.53 10.5
20000 115±2*2.5% 37 10.5 21.1 106 0.53 H-L
25000 121±2*2.5% 38.5 11 24.6 126 0.48 18-19
31500 29.4 149 0.48 M-L
40000 34.8 179 0.44 6.5
50000 41.6 213 0.44
63000 49.2 256 0.40

Note l: High, medium and low voltage winding capacity allocation is (100/100/100)% high, medium and low.
Note 2: The connection group label can be YNd11y10 as required.
Note 3: According to the user’s requirement, medium voltage can be selected as different from the voltage value in the meter or with taps.
Note 4:-5% tapping position is maximum current tapping.
Note 5: For boost transformer, it is advisable to adopt non-tapping structure. If the operation requires, tapping can be set up.
Note 6: When the average annual load rate of transformer is about 45%, the maximum operating efficiency can be obtained by using the loss value in the table.

Rated
Capacity
(kVA)
Voltage Combination Vector Gourp No-load Loss Load Loss No Load
Current
Short Circuit
Impedance
%
HV
(kV)
LV
k(V)
kW kW %
6300 8.00 35.0 0.64 10.5
8000 9.60 42.0 0.64
10000 6.3
6.6
10.5
11
11.30 50.0 0.59
12500 6.6 13.40 59.0 0.59
16000 10.5 16.10 73.0 0.55
20000 110±8*1.25% 11 YNd11 19.20 88.0 0.55
25000 21 22.70 104 0.51
31500 27.00 123 0.51
40000 32.30 156 0.46 12-18
50000 38.20 194 0.46
63000 45.40 232 0.42

Note 1: On-load tap-changer, temporarily providing step-down structure products.
Note 2: According to user’s requirements, other voltage combination products can be provided.
Note 3:-10% tapping position is maximum current tapping.
Note 4: When the average annual load rate of transformer is between 45% and 50%, the maximum operating efficiency can be obtained by using the loss value in the table.

6300-63000kVA three phase two winding OLTC power transformer
Rated
Capacity
(kVA)
Voltage Combination Vector Gourp No-load Loss Load Loss No Load
Current
Short Circuit
Impedance
%
HV
(kV)
LV
k(V)
kW kW %
6300 9.6 44.00
8000 11.5 53.00
10000 6.3 13.6 62.00
12500 33 6.6 16.1 74.00 H-M
16000 36 10.5 19.3 90.00 10.5
20000 110±8*1.25% 37 11 YNyn0d11 22.8 106 H-L
25000 38.5 21 27.0 126 18-19
31500 32.1 149 M-L
40000 38.5 179 6.5
50000 45.5 213
63000 54.1 256

Note 1: On-load tap-changer, temporarily providing step-down structure products.
Note 2: High, medium and low voltage winding capacity allocation is (100/100/100)% high, medium and low.
Note 3: The connection group label can be YNd11y10 as required.
Note 4:-10% tapping position is maximum current tapping.
Note 5: According to user’s requirement, medium voltage can be selected as diferent from the voltage value in the meter or with Note 5: When the average annual load rate of transformer is about 47%,the maximum operating efficiency can be obtained by using the loss value in the table.

Rated
Capacity
(kVA)
Voltage Combination Vector Gourp No-load Loss Load Loss No Load
Current
Short Circuit
Impedance
%
HV
(kV)
LV
k(V)
kW kW %
6300 8.00 35.0 0.64 10.5
8000 9.60 42.0 0.64
10000 11.30 50.0 0.59
12500 6.3
6.6
10.5
11
13.40 59.0 0.59
16000 6.6 16.10 73.0 0.55
20000 110±8*1.25% 10.5 YNd11 19.20 88.0 0.55
25000 11 22.70 104 0.51
31500 21 27.00 123 0.51
40000 32.30 156 0.46 12-18
50000 38.20 194 0.46
63000 45.40 232 0.42

图片3

 


Product detail pictures:

Buy S11 Oil-Immersed Transformer Suppliers –  110kV level three-phase on-load tap-changing power transformer  – JSM TRANSFORMER detail pictures

Buy S11 Oil-Immersed Transformer Suppliers –  110kV level three-phase on-load tap-changing power transformer  – JSM TRANSFORMER detail pictures

Buy S11 Oil-Immersed Transformer Suppliers –  110kV level three-phase on-load tap-changing power transformer  – JSM TRANSFORMER detail pictures

Buy S11 Oil-Immersed Transformer Suppliers –  110kV level three-phase on-load tap-changing power transformer  – JSM TRANSFORMER detail pictures

Buy S11 Oil-Immersed Transformer Suppliers –  110kV level three-phase on-load tap-changing power transformer  – JSM TRANSFORMER detail pictures


Related Product Guide:

Generally customer-oriented, and it's our ultimate goal for being not only the most trusted, trustable and honest provider, but also the partner for our customers for Buy S11 Oil-Immersed Transformer Suppliers – 110kV level three-phase on-load tap-changing power transformer – JSM TRANSFORMER , The product will supply to all over the world, such as: The Swiss, Swiss, Czech, Based on products and solutions with high quality, competitive price, and our full range service, we have accumulated experienced strength and experience, and we've built up a very good reputation in the field. Along with the continuous development, we commit ourselves not only to the Chinese domestic business but also the international market. May you moved by our high quality items and passionate service. Let's open a new chapter of mutual benefit and double win.